NEW QUESTION 115
Identify the missing word in the following sentence. A member of the Project Board is responsible for [ ? ] assurance.
- A. product
- B. quality
- C. risk
- D. supplier
Answer: D
NEW QUESTION 116
Which is an objective of the Closing a Project process?
- A. Assess any benefits that have already been realized
- B. Produce a Benefits Review Plan to identify what benefits are expected
- C. Prepare the plan for the next stage
- D. Check that all benefits are realized before closing a project
Answer: A
NEW QUESTION 117
Which is a minimum requirement for applying the risk theme?
- A. Team managers must maintain their own risk registers
- B. Threats must be assessed for their impact on the viability of the project
- C. A single role that is responsible for all risks must be defined
- D. The PRINCE2 risk management procedure must be followed
Answer: B
Explanation:
Section: Volume B
Explanation/Reference: https://www.prince2primer.com/prince2-2017-risk-theme-changes/
NEW QUESTION 118
Which is a purpose of a Project Product Description?
- A. Document the project mandate and gain approval for the project from the Project Board
- B. Define the quality required of the project's product
- C. Form part of the Work Package for the project product
- D. Provide the initial project budget to be refined in the Business Case
Answer: B
NEW QUESTION 119
Which is a purpose of the 'managing a stage boundary' process?
- A. To enable the project board to approve the continuation of the project
- B. To exercise overall control over the project while delegating day-to-day management
- C. To define the work that needs to be done to deliver the project product
- D. To assign work to be controlled by the team manager
Answer: A
Explanation:
Section: Volume B
Explanation/Reference: http://prince2.wiki/Managing_a_Stage_Boundary#Objective
NEW QUESTION 120
Who represents the three project interests on a project?
- A. Project Support
- B. External project stakeholders
- C. Project Board
- D. Project Manager
Answer: C
NEW QUESTION 121
Which is a purpose of the Managing a Stage Boundary process?
- A. Provide the Project Board with sufficient information for approving the next stage
- B. Review and close any risks and issues identified during the previous stage
- C. Approve the next Stage Plan
- D. Control the link between the Project Manager and the Team Manager(s)
Answer: A
Explanation:
Section: Volume B
NEW QUESTION 122
Which statement about risks is FALSE?
- A. A risk that could have a positive impact on a project's objectives is known as an opportunity
- B. A risk is an uncertain event that, should it occur, will have an effect on a project's objectives
- C. A risk that a project's product is incomplete is known as an off-specification
- D. A risk that could have a negative impact on a project's objectives is known as a threat
Answer: C
NEW QUESTION 123
Which is a minimum requirement for applying the quality theme?
- A. To use user stories to inform the project product description
- B. To use external quality standards for quality control
- C. To use the prescribed approach to quality management
- D. To use lessons to inform quality planning
Answer: C
Explanation:
Explanation/Reference:
Reference http://prince2.wiki/Quality
NEW QUESTION 124
Identify the missing words in the following sentence.
When proposed changes [ ? ], the change authority must refer the decision back to the project board.
- A. exceed the agreed change budget
- B. are objected to by team members
- C. are rejected by the change authority
- D. are below the agreed change budget
Answer: A
Explanation:
Section: Volume B
NEW QUESTION 125
How many tasks does the product-based planning technique describe?
- A. Two
- B. Four
- C. One
- D. Three
Answer: B
Explanation:
Section: Volume B
NEW QUESTION 126
Which is a recommended quality review team role?
- A. Chair
- B. Producer
- C. Assurance
- D. Project Manager
Answer: A
Explanation:
Section: Volume B
NEW QUESTION 127
What theme provides the justification for the project?
- A. Progress
- B. Plans
- C. Business Case
- D. Quality
Answer: C
NEW QUESTION 128
Which describes an off-specification?
- A. A prototype demonstrating a possible design solution
- B. The production of more than the defined quantity of a specialist product
- C. An interdependency between products that was previously unidentified
- D. The addition of an improvement to a product description
Answer: C
Explanation:
Explanation
Reference https://www.prince2primer.com/prince2-change-control/
NEW QUESTION 129
Which is a PRINCE2 time-driven control?
- A. End Stage Report
- B. Project Initiation Documentation
- C. Project Brief
- D. Checkpoint Report
Answer: D
NEW QUESTION 130
Which role is responsible for the quality of the specialist products delivered in the project?
- A. Executive
- B. Senior user
- C. Senior supplier
- D. Project assurance
Answer: C
Explanation:
Section: Volume B
Explanation/Reference: http://www.fmdconsultants.co.uk/p2_roles_and_responsibilities_v01.docx
NEW QUESTION 131
......